Broken Hill Parks Stormwater Irrigation Project
Broken Hill City Council commissioned Darling Irrigation via a competitive tender process to construct a storm water capture and re-use project for O’Neill Park Soccer Fields and AJ Keast Park.
Project overview
Broken Hill City Council engaged Darling Irrigation to design and install water-efficient irrigation systems at AJ Keast Park and the O’Neill Park Soccer Fields.
Both sites had previously been watered using manually moved impact sprinklers. This method used water inefficiently and required approximately 10 hours of volunteer labour each week.
The two sites were developed as a pilot project for the future upgrade of approximately 25 parks and sporting ovals across Broken Hill. The broader program was forecast to save the Council more than 300 megalitres of water each year in a region where water availability and supply costs are significant concerns.
The challenge
The project involved capturing, storing and reusing stormwater while preserving existing park infrastructure and keeping both sites functional.
Construction challenges included:
• Restricted access for machinery and concrete trucks
• Extensive rock beneath sections of the sites
• Working around existing water mains, utilities and optic fibre
• Maintaining a live water supply throughout construction
• Protecting the appearance and usability of public recreation areas
• Coordinating staff and contractors across a remote location
At AJ Keast Park, access limitations meant a four-tonne excavator was the largest machine that could enter the site. Removing the existing underground tank alone took four days, while specially constructed ramps were needed to provide access for concrete trucks.
The solution
Darling Irrigation delivered the project to specification over a two-month construction period.
Seven Darling Irrigation employees worked on site using a 12-days-on, four-days-off roster to accommodate the significant travel distances. Local contractors were also engaged for electrical work, surveying, concreting, spoil removal and wet plant hire.
Both systems were designed to capture stormwater, store it and distribute it through subsurface KISSS irrigation systems. Toro MM4000 controllers provide remote operation, monitoring and fault alerts.
AJ Keast Park
AJ Keast Park is a public recreation area located within a built-up, high-pedestrian-traffic area. Maintaining the park’s visual appeal was an important part of the project.
Stormwater runoff from the large hill behind the park is captured and stored in an underground, load-bearing concrete tank. Lawn was reinstated above the tank, leaving the park’s usable green space and appearance largely unchanged.
Stored water is filtered and pumped through a subsurface KISSS drip irrigation system, with the control equipment housed in an existing shed.
System specifications include:
• Approximately 4,200 square metres of irrigated area
• A 120-kilolitre underground storage tank
• Grundfos APG.50 sump pump delivering 2.5 litres per second at 43 metres head
• Arkal Spin Klin M224 120-mesh filtration
• Approximately 5,300 metres of KISSS dripline
• Dripline output of 1.6 litres per hour at 0.5-metre spacing
• Laterals installed 0.8 metres apart
• Toro MM4000 remote irrigation controller
Level probes maintain approximately one-third of the tank’s capacity using town water when stormwater supplies are low. Excess water is directed into the town drainage system.
O’Neill Park Soccer Fields
O’Neill Park includes two full-sized soccer pitches, a warm-up area and a spectator hill.
The system was designed to collect stormwater from surrounding drains, direct it through a wetland and then pump it into two above-ground concrete storage tanks. The stored water is filtered and distributed through a subsurface KISSS irrigation system across the playing fields, warm-up area and spectator hill.
The slope of the spectator area, rocky ground conditions and the need to install drainage infrastructure through a developed area added complexity to the design and construction process.
System specifications include:
• Approximately 20,000 square metres of irrigated area
• Two 105-kilolitre above-ground storage tanks
• Grundfos CRN10-06 pump with variable-frequency drive
• Pumping capacity of 2.5 litres per second at 38 metres head
• Arkal M224 Spin Klin 120-mesh filtration
• Approximately 25,500 metres of KISSS dripline
• Dripline output of 1.6 litres per hour at 0.5-metre spacing
• Laterals installed 0.8 metres apart
• 12 irrigation control valves
• Toro MM4000 remote irrigation controller
Level probes maintain approximately one-third of the storage capacity using town water when required.
The result
Darling Irrigation completed the project to specification within the two-month construction program.
The new systems have significantly reduced the manual labour required to irrigate both sites while improving water-use efficiency and supporting healthier, more consistently maintained public spaces.
By capturing and reusing stormwater, the project also demonstrated a practical model for reducing reliance on town water across Broken Hill’s wider network of parks and sporting facilities.